3.	LOGISTICS:   WE REMAIN IN EXCELLENT SHAPE IN FUELS SUPPORT,
WITH OUR AVERAGE DAILY INVENTORY OF JET FUEL RUNNING AROUND [(b)(1)sec3.4(b)(5)]
	GALLONS.  WE HAVE FOUR R-14 BLADDER SYSTEMS IN OPERATION ON
THE A-10 SIDE OF THE AIRFIELD AND ARE IN THE PROCESS OF INSTALLING
ANOTHER ONE ON THE AFSOC SIDE.  WE UNDERSTAND KING FAHD WILL BE THE
APOD FOR A LARGE NUMBER OF ARMY FORCES.  COMM ALF AND 101AD/LG
MEETING IS SCHEDULED 8 DEC TO WORK OUT ARMY/ALCE RAMP SPACE
ALLOCATION.

A.	WAR READINESS SPARES KIT (WRSK):  FILL RATE FOR WRSK CELLS
REMAINS ABOVE 80 PERCENT.  HARD WRSK ASSETS ARE AT THE 90 PERCENT
LEVEL.

B.	TRANSPORTATION:  GOVERNMENT VEHICLE IN-COMMISSION RATE IS AVERAGING ABOVE 90 PERCENT WITH A FLEET OF 435 VEHICLES.

C.   (U)   FINANCIAL POSITION:  PAY ADVISORIES ARE NOW GETTING TO US IN



PAGE 06 RHIEFBA0355
A VERY TIMELY MANNER AND WE WERE PLEASANTLY SURPRISED WHEN LEAVE AND
EARNINGS STATEMENTS SHOWED UP.  A BIG THANKS TO THE CENTAF/AC STAFF
FOR THEIR EFFORTS IN BOTH AREAS.

D.	CONTRACTING POSITION:  THE DECISION OF THE SAUDIS TO FUND
OUR TRANSPORTATION AND FACILITIES REQUIREMENTS AND THE RESULTANT
CHANGE REQUIRING OUR CONTRACTS IS FINALLY OFF TO A SHAKY START.
THREE WEEKS AGO, WE PUT OUR FACILITY AND VEHICLE REQUIREMENTS TO
SUPPORT THE THREE INBOUND A-10 UNITS (ONE OF WHICH IS ALREADY HERE),
THE IMMINENT APOE/APOD SURGE AT KING FAHD AND ACTIVATION OF OUR NEW
FOL AT KKMC INTO THE SAUDI CONTRACT APPROVAL SYSTEM.  WE EMPHASIZED
THAT THESE REQUIREMENTS WERE URGENT, BUT WE HAD NO MOVEMENT ON ANY OF
OUR REQUESTS UNTIL 7 DEC WHEN WE RECEIVED GO AHEAD TO PURCHASE
TRAILERS FOR OPS AND AMU OPERATIONS.  WE ARE STILL WORKING THE
VEHICLE REQUIREMENTS, ETC.  HOPEFULLY, THE SYSTEM WILL BECOME MUCH
MORE RESPONSIVE.

E.	PROBLEM:  SHORTAGE OF RELIABLE ALL TERRAIN FORKLIFTS.