Document Page: First | Prev | Next | All | Image | This Release | Search

File: aacak_03.txt
Page: 03
Total Pages: 5

AIM 9				234

30MM HEI			291,100

RR-136 CHAFF			16,834

LUU-1 / LUU-5			4728

LUU-2				7292

AGM-65D			1628

RR-170 CHAFF			558,138

MK84 AIR			1100

MK84 LD			2483

30MM CBT MIX		715,356

RR-141 CHAFF			38,427

RR-119				16,096

2.75 WP RX			6500

  * AIRLIFT TO AOR REQUESTED.
**AIRLIFT COMPONENTS, SEALIFT BOMB BODIES.
  3. - ENGINEERING AND SERVICES: USCENTAF/DE TOP PRIORITIES ARE:
   . .
  FORCE BEDDOWN, OPERATION SUPPORT, AND TRANSITION FROM TENTAGE TO
  . .
  TEMPORARY FACILITIES. CURRENT EMPHASIS IS CONCENTRATED ON OPENING
  
NEW BEDDOWN SITE AT AL KHARJ.  IN ADDITION, EXISTING SITES WITH

PROJECTED AIRCRAFT GAINS WILL REQUIRE PRIORITY CONSTRUCTION.

  A.~ FIRE PROTECTION: P-19 CRASH TRUCK NON AVAILABLE AT AL

  KHARJ.
  B~ PRIME RIBS: FIFTEEN TABLE MIXING MACHINES RECEIVED AT
  THUMRAIT. THIRTEEN WILL BE REDISTRIBUTED TO SITES. REQUEST TAC/BS

  DE EXPEDITE DELIVERY OF REMAINING 17 MIXERS-TO RIYADH VS THUMRAIT.

   C       PRIME FARE: RATION STATUS: 
                   MEALS                 DAYS              THEATER

   RATION       ON-HAND             SUSTAINABILITY      RESERVES
                     .
   B             4,032,614                            63                                     1,920,000
   MRE        1,872,669                 59                                                 960,000