U.S. ARMY INFORMATION SYSTEMS COMMAND
FT. HUACHUCA, AZ 85613-5000
LESSONS LEARNED
KEYWORD; SUPPLY EXERCISE: ODS
SUBJECT: EOU REQUIREMENT VALIDATION FOR 653RD SIGNAL CO (NO).
POC: SFC JOSEPHINE OLSON
DSN: 879-6925 COMMERCIAL: 602-538-6925
OBSERVATION: ENVIRONMENTAL CONTROL UNIT (ECU) REQUIREMENT FOR 653RD SIGNAL
COMPANY DISAPPROVED BY HQDA.
DISCUSSION: PRIOR TO DEPLOYMENT OF THE 653RD SIGNAL COMPANY, WE LEARNED THAT
THEY DID NOT HAVE ANY ECUS FOR THEIR VANS AS THEY WERE NOT AUTHORIZED
ITEMS OF EQUIPMENT. ECUS WERE LOCATED, BUT ON-HAND GENERATORS WERE NOT LARGE
ENOUGH TO HANDLE BOTH THE VAN EQUIPMENT AND THE AIR CONDITIONERS THE 653RD
ATTEMPTED TO GET LARGER GENERATORS (30XW) UNITS ISSUED FROM THE FLORIDA NGB,
BUT THE REQUEST WAS DISAPPROVED BY HQDA. THE REASON WAS THERE WAS NOT A VALID
REQUIREMENT FOR THE UNIT TO HAVE THE LARGER GENERATORS. LACK OF ECUS OR
ADEQUATE ECUS WAS ONE OF THE FIRST PROBLEMS EXPERIENCED BY THE 11TH SIGNAL
WRIGADE IN SWA DURING THE AUGUST - SEPTEMBER 90 TIME FRAME. THUS.-THE NEED
HAD ALREADY BEEN VALIDATED BASED ON FIRST HAND EXPERIENCE BY UNITS IN THE AOR.
LESSON LEARNED: THE NEED FOR ECUS AND PROPER POWER GENERATING EQUIPMENT IN
VAN MOUNTED SIGNAL EQUIPMENT HAD ALREADY BEEN DEMONSTRATED BY IITH SIGNAL BDE
UNITS DURING THE EARLY PART OF THIS OPERATION. REQUIREMENTS SUCH AS THESE
SHOULD BE GENERATED FROM THE BOTTOM UP. ECUS AND POWER TO OPERATE
THEM IN A SIUATION AS THIS IS NOT A LUXURY, BUT A NECESSITY DUE TO THE HARSH
WEATHER CONDITIONS.
RECOMMENDED ACTION; ENSURE THAT UNITS HAVE PROPER ENVIRONMENTAL EQUIPMENT AND
APPROPRIATE POWER SUPPLIES DICTATED BY WEATHER CONDITIONS WHERE THEY WILL
OPERATE.
CGMMENTS: