SUBJECT:  1706 PAREFW ENGINEERING/FIRE PROTECTION/STATUS

EXT RCVD

RAASZYHW RHIDFRA0254 3201650-              --RHIUFAA.
ZNY
R 162200Z NOV 90
FM 1706 PAREFW//DE//
TO RHIUFAA/HQ USCENTAF FWD//DE/LG//
INFO RUCUBBB/HQ SAC OFFUTT AFB NE//SBS/DER/LG//
RHDIAAA/HQ USCENTAF LANGLEY AFB VA//DE/LG//
BT

SUBJECT:  ENGINEERING/FIRE PROTECTION/STATUS
1.  (U)  ENGINEERING
A.        PRIME BEEF:
CURRENT:  54 PERSONNEL
PROJECTED:  6

B.        WATER STATUS:
INSTALLED.  WE ARE CURRENTLY DOING BULK CLORINATION TO MAKE
WATER POTABLE BUT STILL WAITING ON SUPPORT KIT FOR ROWPU.
HAVE TWO SMPTS BUT ONLY ONE 40 FOOT TRAILER.
QTY/DAY LOCAL:  BOTTLE DRINKING WATER UNLIMITED
DIST SYS STATUS:  INSTALLED
TREATMENT STATUS:  INSTALLED-WAITING ON FILTERS AND SUPPORT
KIT.

PAGE  02  RHIDFKA0254
ROWPU:  ONE ON SITE/NOT OPERATIONAL
ERD STATUS:  NOT REQ'D
STORAGE CAPACITY:  SIX 20 KGAL BLADDERS ON SITE AND INSTALLED.
SANITARY STATUS:
LOCAL SYS:  NOT AVAILABLE
FIELD SYS:  FOUR FIELD UNITS/INSTALLED/OPERATIONAL
SHOWER/SHAVE STATUS:  4 INSTALLED/OPERATIONAL
LOCAL SYS AVAIL/QTY:  NONE
WASTE MGMT SYS:  LAGOON CONSTRUCTED.  DISTRIBUTION SYSTEM
COMPLETE.
C.               POWER STATUS:  HIGH VOLTAGE SYSTEM IS OPERATIONAL.
POWER PLANT OPERATION 24 HOURS/DAY.
3 GENERATORS OPERATIONAL AT OPS FACILITIES.  INSTALLING HIGH
VOLTAGE LINES TO OPS FACILITIES.
COMMERCIAL AVAIL/CAP:  NONE
DISTRIBUTION SYS CAP:  INSTALLED/OPERATIONAL.
GENERATOR QTY/CAP:  3-5 KW, 8 EA 60 KW, 11 EA 100 KW, 3 EA
750 KW.
D.              ATH HOSP STATUS:  ONE CLINIC ERECTED.  ALSO ONE TENT
HAS BEEN ERECTED AS A WARD.  AIR TRANSPORTABLE HOSPITAL (ATH)