SUBJECT:  CIVIL ENGINEERING/PRIME BEEF

ROUTINE							DATE:
								TIME:


         
RAASZYUW RHIDFKA0254 3201650-        --RHDIBFF.
ZNY
R  162200Z NOV 90
FM 1706 PAREFW//DE//
T0 RHIUFAA/HQ USCENTAF FWD//DE/LG//
INFO RUCUBBB/HQ SAC OFFUTT AFB NE//SBS/DER/LG//
RHDIAAA/HQ USCENTAF LANGLEY AFB VA//DE/LG//
BT
         
SUBJECT: ENGINEERING/FIRE PROTECTION/STATUS
1. (U) ENGINEERING
A.       PRIME BEEF:
CURRENT:  54 PERSONNEL
PROJECTED: 6
         
B.      WATER STATUS:
INSTALLED. WE ARE CURRENTLY DOING BULK CLORINATION T
WATER POTABLE BUT STILL WAITING ON SUPPORT KIT FOR R
HAVE TWO SMFTS BUT ONLY 0NE 40 FOOT TRAILER.
QTY/DAY LOCAL: BOTTLE DRINKING WATER UNLIMITED
DIST SYS STATUS: INSTALLED
TREATMET STATUS: INSTALLED-WAITING ON FILTERS AND SUPPORT
KIT.
         
PAGE  02 RHIDFKA0254
ROWPU: ONE ON SITE/NOT OPERATIONAL
ERD STATUS: NOT REQ'D
STORAGE CAPACITY: SIX 20 KGAL BLADDERS ON SITE AND INSTALLED.
SANITARY STATUS:
LOCAL SYS: NOT AVAILABLE
FIELD SYS: FOUR FIELD UNITS/INSTALLED/OPERATIONAL
SHOWER/SHAVE STATUS: 4 INSTALLET/OPERATIONAL
LOCAL SYS AVAIL/QTY: NONE
WASTE MGMT SYS: LAGOON CONSTRUCTED. DISTRIBUTION SYSTEM
COMPLETE.
C. POWER STATUS: HIGH VOTAGE SYSTEM IS OPERATIONAL.
POWER PLANT OPERATION 24 HOURS/DAY.
3 GENERATORS OPERATIONAL  AT OPS FACILITIES. INSTALLING HIGH
 

        