ROUTINE									PAGE: 2
POWER PLANT OPERATION 24 HOURS/DAY.
3 GENERATORS OPERATIONAL AT OPS FACILITIES.  INSTALLING HIGH
VOLTAGE LINES TO OPS FACILITIES.
COMMERCIAL AVAIL/CAP: NONE
DISTRIBUTION SYS CAP:  INSTALLED/OPERATIONAL.
GENERATOR QTY/CAP:  3-5 KW, 8 EA 60 KW, 11 EA 100 KW, 3 EA

PAGE 3  RHIDFKA0102
750 KW.  WE CAN RETURN 100 KWS FOR USE AT OTHER LOCATIONS.
D.	ATH HOSP STATUS:	ONE CLINIC ERECTED.  ALSO ONE TENT
HAS BEEN ERECTED AS A WARD.  AIR TRANSPORTABLE HOSPITAL (ATH)
 NOT ON STATION.
E.  (U)  VEHICLE STATUS:  3 USAF 4X4 P.U. IN USE AND LOCAL RENTAL
 OF 8 GENERAL PURPOSE VEHICLES.  LOCAL RENTAL OF HEAVY EQUIPMENT
TERMINATED TODAY.  USAF VEHICLES:  2 EA 13 TON AT FORKLIFTS, 2 EA
 SEWER PUMPING TRAILERS, 1 EA D-7 DOZER, 2 EA 10 TRACTOR, 1 EA
 40 FOOT TRAILER, 1 EA TILT TRAILER, 3 EA FLIGHTLINE SWEEPERS.
F.	RRR CAPABILITY: NONE.  MATTING BEING USED IN GP
 SHELTERS AS FLOORING.  3 BUNDLES LEFT.
G.  AIRFIELD STATUS:
PAVE COND/CAP:  LCN 75
BARRIERS: 2 BAK 12'S  2 BAK 14'S
NAV AIDS:  RUNWAY AND MAIN TAXI LIGHTS EXIST BUT ARE MARGINAL
FOR NIGHT OPERATION.  APPROACH AND THRESHOLD LIGHTS INSTALLED.
PLASI OPERATIONAL.  USAF PORTABLE TACAN IS OPERATIONAL.
INSTRUMENT LANDING SYSTEM HAS BEEN FLIGHT CHECKED AND IS OPERATIONAL.
H.	(U)     TENT CITY STATUS:  UNCHANGED EXCEPT THIRD GP SHELTER ERECTED

PAGE 4  RHIDFKA0102
AS WEIGHT LIFTING FACILITY.  ALL TENTS/SHELTERS ARE ERECTED
1. 	SHORTFALLS:
(1)	SUPPORT KIT FOR ROWPU.
(2)	40 FOOT TRAILER FOR WATER RESUPPLY OPERATIONS AND ONE SMFTS
TO REPLACE THE ONE WHICH BLEW A SEAM LONG TERM IS TWO 5,000
TANKERS TRUCK.


ROUTINE									PAGE: 2