SUBJECT:  CIVIL ENGINEERING, FIRE PROTECTION STATUS
ROUTINE

RAASZYUM RHIDFKA0102  3411248-		--RHDIBFF.
ZNY
R 071430Z DEC 90
FM 1706 AREFW (P) // DE //
TO RHIUFAA/HQ USCENTAF FWD // DE/LG //
INFO RUCUAAA/HQ SAC OFFUTT AFB NE // SBS/DER/LG //
RHDIAAA/HQ USCENTAF LANGLEY AFB VA // DE/LG //
BT
SUBJECT: ENGINEERING/FIRE PROTECTION/STATUS
1.	(U)	ENGINEERING
A.	PRIME BEEF:
CURRENT:	57 PERSONNEL (ONE ON EMERGENCY LEAVE BACK TO STATES).  THREE POWER PRO TECHNICIANS ARRIVES THIS WEEK.
PROJECTED:  4
B. WATER STATUS:
INSTALLED.  WE ARE CURRENTLY DOING BULK CHLORINATION TO MAKE 
WATER POTABLE BUT STILL WAITING ON SUPPORT KIT FOR ROWPU.
ONE SMFTS HAS BEEN REPAIRED AND ONLY HAVE ONE 40 FOOT TRAILER.
ONE OF OUR SMFTS BLEW OUT AT A SEAM ON 26 NOV.  IT HAS ALSO BEEN
REPAIRED BUT STILL LEAKS.  RELIABILITY IS QUESTIONABLE.
QTY/DAY LOCAL:  BOTTLE DRINKING WATER UNLIMITED

PAGE 2  RHIDFKA0102
DIST SYS STATUS:  INSTALLED
TREATMENT STATUS:  INSTALLED-WAITING ON FILTERS AND SUPPORT
KIT.
ROWPU:  ONE ON SITE/NOT OPERATIONAL
ERD STATUS:  NOT REQ'D
STORAGE CAPACITY:  SIX 20 KGAL BLADDERS ON SITE AND INSTALLED.
SANITARY STATUS:
LOCAL SYS:  NOT AVAILABLE
FIELD SYS:  FOUR FIELD UNITS/INSTALLED/OPERATIONAL
SHOWER/SHAVE STATUS: 4 INSTALLED/OPERATIONAL
LOCAL SYS AVAIL/QTY:  NONE
WASTE MGMT SYS:  LAGOON CONSTRUCTED.  DISTRIBUTION SYSTEM
COMPLETE.
C.  POWER STATUS:  HIGH VOLTAGE SYSTEM IS OPERATIONAL.












									