		(1) WOC/SRC Update: DE will review progress on HN construction project which is 
currently one week behind schedule. Minimum operational capability is 15 Jan. Fully 
operational facility is expected 31 Jan. Furniture buy is underway. Communications update will 
be provided at CSRB this week (DE, SC, AO).

		(2) Aircraft Parking Pads: The East pad (HN contract) is three days behind. The 
West pad (Red Horse) was supposed to start laying concrete today, but was awaiting materials. 
A worse case/best case parking plan has been approved by TFW/CC (MAA, DE).

		(3) Flightline Fencing: Cost update will be provided at the 
Joint projects Meeting (DE).

		(4) Siren/Alarm System (AO).

			(a) HN agreement needed to reallocate a spare siren system to Site 2. US 
purchase of 2 additional systems will continue and will give them one to replace as a spare. 
In the meantime, will achieve a full siren system capability base wide.

			(b) Flags have been distributed to all units requiring them. LGT will make 
the vehicle mounts. Addltional vehicle flags are available through CSG/AO if needed. Also, HN 
work on the one facility flag near the fire station is underway and should be completed soon 
(AO, DE).

			(c) CSG/CC will release a policy letter announcing the new alarm 
notification system this week. The letter will also be released to the host.

		(5) HN should be included in our training sessions to begin 5
Jan. See discussion at paragraph 6. (CVI)

		(6) Munitions Clearance Vehicles (MCV) (AO). New estimated delivery date is 16 Dec 
at Jebel Ali. We expect delivery here O/A 22 Dec.

		(7) Camouflage, Concealment, Deception (CCD) Priorities (AO). We have 100 woodland 
nets and 1800 desert nets are enroute, but a delivery date is not available.

			(a) Camouflaging Base Headquarters

			(b) False Parking Pad with Silhouettes/Decoys. Includes using woodland nets 
to create additional silhouettes. Pilots report the effect is same as 2D silhouettes.

			(c) Hangar Tonedown: Paint will be used in lieu of nets Dlscussion with HN 
needed on labor and materials

	b. Non Warskills Program A detailed break out of requirements and available manpower 
will be available next meeting So far, there are
more requirements than manpower voluntarily identified (CSG/CD).

	c. ATH Fencing A review of cost and prioritization of labor will
be conducted next week. (DE, SGA)

	d. Multiman Intermediate Cooling System (MICS). AON conducted a
demonstration. A reasonable requirement must be established as soon as
possible. ACTION: AO, ECD: 18 DEC.