          FR    926th Engineer Group/S-3//
          TO    7th Engineer Brigade/S-3//

          SUBJECT; ENGREP DTG 050800 MAE 91


          PART I

          LAST 24 HOURS; 926th EN GP is planning and coordinating MSR clearing,
          upgrade and demolition of enemy equipment and ordnance in assigned
          area of operations (see frago 2-91-02). Completed road
          grading to Ist, 2nd and 3rd BDES. Completed carpentry work
          for 3AD Rear. Currently have TASS line communications with BDE; and
          RATT communications with 19th and 92d. Upgraded 4 miles of MSR to
          DISCOM with aces and grades. Destroyed four trucks near the Igth
          perimeter by burning.

          MSR status: IPSA Road for the 30 00.00 lat line to IUK rear boundary
          is operational, 2 lane, asphalt. MSR Jaguar QT 220975 to QT315870 is
          operational, single lane marl surface. Recon of other MSRs will
          continue today. Reports will be submitted as recons are complete.

          NEXT 24 HOURS: Igth EN BN will begin demolition of IZ equipment in
          A/0 of EWL Montgomery (see 926th FRAGO 2-91-02). The 92d will begin
          MSR upgrading of an unidentified road that runs along the E-W grid
          line 3 in PU. Road starts at IPSA road and goes to approximately the
          46 30.00 lon line. The 92d will also begin recon of possible hard
          surface MSR out of 3AD section to the Basrah/Kuwait highway.
          Scheduled to coordinate with USAF to provide fire and rescue support
          to the C-130 operation along the Basrah-Xuwait highway between the
          QU585040 and QT 9 grid line. Will evaluate the well completion kit
          received against well site problems reconned yesterday.

          PROBLEM AREAS: The Group is still in need of haul and
          transportation assets. Well completion kit is also needed for Class I
          water production in 3AD sector ASAP.

          PART 11: The rating of the Group overall is      GREEN.

       A.   Unit  Locations
                     (1)   Group HQ              N29 25.60    E047 05.70      QUO28130
                           (a) Igth EN BN        N30 12.03    E047 01.02      PUO45430
                           (b) 92d EN BN(-)      U29 25.60    E047 05.70      QUO28130
                           (L) 5694th FF         N29 25.80    E047 05.70      QUO28130
                           (d) 747th EN DET      N29 25.60    E047 05.70      QUO28130



                B.   Unit Status (Note:

                                               Line I     Line 2     Committed    72hrs
                (1)  Cdr's Assessment          GREEN       GREEN
                (2)  Eff Line Platoons         18/18      18/18         6/18      9/18
                (3)  Dozers                    21/26      21/26       11/26       15/26
                (4)  Loaders, Scoops           16/17      16/17       13/17       13/17
                (5)  Tractors/Trlrs            18/24      18/24       16/24       16/24
                (6)  Graders                   12/13      12/13       10/13       10/ 13
                (7)  Water Distr.                5/8        5/8        5/8        5/8

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 2 f:/Week-24/BX000211/SITUATION REPORTS 926TH ENG GP 14 FEB-5 MAR 91/engrep:10189613570318
Control Fields 17
File Room = jun96_declassified
File Cabinet = Week-24
Box ID = BX000211
Unit = VII CORPS
Parent Organization = ARCENT
Folder Title = SITUATION REPORTS 926TH ENG GP 14 FEB-5 MAR 91
Folder Seq # = 11
Subject = ENGREP
Document Seq # = 2
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 18-OCT-1996