                                                         HQS, 7TH ENGINEER BRIGADE
                                                         DTO 671500 JAN 91



              1. Daily Corps SITREP.

                  a. Situation! We are 40% complete on one tapline road
              overpass at PS1531. Trying to move the 92nd up to Log Base Echo
              area so  that when the location is established we can begin work.

                  h.   Operations/Tng. Construction Mission Status:

                       (1)  VII Corps Tank Range--Gg%
                       (2)  3AD Airfield--100%
                       (3)  207th MI Beinis--100%
                       (4)  TF8-43 ]3epm8--100%
                       (5)  12th Evae gpt--100%
                       (6)  Corps Obstacle Range--50%

                  e. Combat Support Equipment Readiness 91%

                  f.   Personnel


                          # Pers in          % in            Pers
                         Theater           Theater         in TAAs


                            4,691           57%             4.646

                  g.   Unit Locations!

                       HQg, 7th EN BDE PS445145
                       176 EN GP          PS425125
                       926 EN GP          M9560560


                  h. Problem Requiring Corps Assistance:

                       Priority 1--In order to complete Log Base Echo on time,
              the 92nd Engineer Battalion must have additional het assets to
              get the line companies of 92nd out to Log Base Echo to begin
              work.


                       Priority 2--Must get transportation for 14 MILVANS of
              Class IV Barrier Material to haul out to Corps obstacle range by
              8 January 1991 or the construction of the range will be delayed.

              2. POC S-3, 7th Engr Ede 9-7598-718.

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 41 f:/Week-24/BX000213/SITUATION REPORTS 7TH ENG BDE 22 DEC 90- 10 APR 91/daily sitrep 7th engineer bde:11089615143325
Control Fields 17
File Room = jun96_declassified
File Cabinet = Week-24
Box ID = BX000213
Unit = VII CORPS
Parent Organization = ARCENT
Folder Title = SITUATION REPORTS 7TH ENG BDE 22 DEC 90- 10 APR 91
Folder Seq # = 1
Subject = DAILY SITREP 7TH ENGINEER BDE
Document Seq # = 5
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 08-NOV-1996