Subject = OPERATIONS DESERT SHIELD 82D ENGINEER BATTALION 28 AUG 91
Box ID = BX000301
Folder Title = 82D ENG BN AFTER ACTION REVIEW COMMENTS 5 APR 91
Unit = VII CORPS
Parent Org = ARCENT
22. PROJECT: Hasty decontamination site, Dec 90.
DESCRIPTION: Constructed a hasty decontamination site for 82nd
Engineer Battalion.
EQUIPMENT: SEE - 2 hours
MAN HOURS: 2
UNIT: C Company, 82nd Engineer Battalion
23. PROJECT: 2 Squadron, 2nd Armored Cavalry Regiment(2ACR) small
arms/tank range, Dec 90.
DESCRIPTION: Constructed 500 meters of berm to support a
Squadron small arms/tank range.
EQUIPMENT: Dozer - 2 hours
MAN HOURS: 24
UNIT: A Company, 82nd Engineer Battalion
24. PROJECT: Military Supply Route(MSR) for Regimental Support
Squadron(RSS).
DESCRIPTION: Constructed 21 km of two lane MSR for the RSS.
EQUIPMENT: Grader - 128 hours
MAN HOURS: 128
UNIT HHC, 82nd Engineer Battalion
25. PROJECT: Perimeter trenches for RSS Base Camp.
DESCRIPTION: Constructed 2000 meters of 'V' ditch around two
base camps and the RSS.
EQUIPMENT: Graders - 8 hours
MAN HOURS: 8
UNIT: HHC, 82nd Engineer Battalion
26. PROJECT: Clean up oil spill
DESCRIPTION: Constructed approximately 500 meters of berm to
contain an oil spill along tap line road.
EQUIPMENT: Dozer - 32 hours
MAN HOURS: 32
UNIT: C Company, D Company, 82nd Engineer Battalion