Subject = OPERATIONAL SUMMARY 24 FEB 91 G DAY
Parent Organization = CENTCOM
Unit = ARCENT
Folder Title = COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL
Document Number = 5
Box ID = BX000525
5) Harzard Marking T@i@: contractor delivered red/white
diagonal plastic tape on 26 Feb to 416th ENCC14.
6) Barbed Wire: RCCM procuring 20,000 spools through Host
Nation; delivery to start I Mar to IDGRASE BRAVO. 14,000 of 45,000 each
1.7m rebar pickets delivered to IMC on 27 Feb.
j) contract Status: Reviewing all unstarted construction
projects for need and suitability; will provide input to CENTCM by 4
Mar. Initiated staff action to start Construction Project Review (CPR)
Board at HQ, ARCERR.
K) MSR Status:
West Range Road - Amber, 43 EN EN's is now ECD 1 Mar
East Range Road - Red, has been deferred.
SE Dodge - Green, shoulder work revised EM is 24 Feb due to
rain delay/damge.
NW Dodge - Green, cold patch work casing minimal traffic
disruption.
Sultan(Nash) - Green
NW Old Tapline - Green
SE Old Tapline -- Green
XVIII ABN Corr)s KIMS to IOGBASES FOW and OSCAR
Georgia - Amber 6 lanes; due to rain
Montana - Green 6 lanes good to border
Te@@ - Green 2 lanes; due to rain
Chio - Gmm 2 lanes good along border
Virginia - Green 2 lanes gravel
Colorado - Green 2 lanes gravel
VII Corr)s KEY MRs
Green and Blue - Amber both have 10-15 inud holes on each
MSR; plan is to have 109th EN V-ditch drainage.
Black - Green - 2 lanes gravel
L) Displaced Citizen Cwnps: G4/Engineer Task Force on
facility and logistics support for DCs in Iraq and Kuwait ompleted.
ODNPIM published and distributed. USAID shelter material for DCs and
EPWs being flown from Carp Darby, Italy on C-130s. Two flights arrived
DHABRAN 26 Feb with 810 rolls. One flight with 190 rolls due 28 Feb
Provided 22rid SUPOOM, Acsim, the allocation request. It appears from
present situation that no camps are required; will confirm with G5.
M) Life Support Area:
Nam %Ccmlete BrD Water Well
I
Document Page:
First |
Prev |
Next |
All |
Image |
This Release |
Search
Document 99 f:/Week-33/BX000525/COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL/operational summary 24 feb 91 g day:04189716374911
Control Fields 17
File Room = aug96_declassified
File Cabinet = Week-33
Box ID = BX000525
Unit = ARCENT
Parent Organization = CENTCOM
Folder Title = COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL
Folder Seq # = 9
Subject = OPERATIONAL SUMMARY 24 FEB 91 G DAY
Doc Seq # = 5
Doc Date =
Scan Date =
Queued for Declassification = 25-AUG-1996
SAGWI Request = 10-APR-1997
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 18-APR-1997