Subject = OPERATIONAL SUMMARY   24 FEB 91 G DAY                           

Parent Organization = CENTCOM     

Unit = ARCENT      

Folder Title = COMMAND REPORT  AFTER ACTION REPORT ENGINEER GE CELL                                            

Document Number =          5

Box ID = BX000525







                              M) Life Support Area:

                     Name                           -%Ccmlete                     Water Well
                     17IA                               38%            910415           0%
                     Rieonix City                       90%            910318         55%
                     Bastogm                            96%            910318         90%
                     I;udowici                          99%            910318         75%
                     Abqaiq                             94%            910318         95%
                     Pulaski                            97%            910318         70%

                     NOTE: Contract awarded for POWPU supply.

                     B. EAC/416'IH ENOON: Engineer Status Report #61 02093OZ MAR 91 and
                Cmmk-eider's SITREP #75 02093OZ MR 91

                         A) CLO@M OPERATICNS: Range Road is Amber. 43D EN BN continues
                to repair a sub-base failure; BCD is 15 MAR to initial standards.           SE MSR
                Dodge is Green. The shoulder repair is complete. 224 of 224RM have been
                repaired. The shoulder will require continuous maintenance.            All other
                roads still green.     SWAPDOP - Pipeline project: Phase V 80% 177KM of
                rigid pipe has been installed. Quartermaster has ceased hauling pipe to
                complete this segment, the line has been successfully tested to Pump
                Station #7. EPW COMPOLNDS:       Eastern Site: Camp #IA 90% continuing
                installation of force main and check valves. Facility will be reported
                complete once all engineer tasks are ccaplete including lighting and
                sanitary facilities. Western Site: #2 85% Engineer effort on site is
                complete. 'Ihere are 22 tmj'ers, 320 latrines, and 135 showers on site.
                Digging sumps and improving roads continues. The sanitary lagoon is
                complete. Additional requirements for EPW processing are underway. #2A
                80% 100% of camp is bermed. The sanitary lagoon is ccaplete. Additional
                retiirmmts for IEPW processing are undexway.

                         B) ENGINEER ISSLJES: Class IV Update: lW4C - Aggregate continues
                to be hauled to MSR Green with no interruption on flow; a total of 32,000
                cubic meters of aggregate is to be delivered to Patriot Sites. Additional
                aggregate has been requested. 144 cubic meters of concrete is scheduled
                to be delivered,2 MAR 91, for the Air Force constructed K-Span.

                         C) PRIOR= OF WOIU<: Priority is to pipelines, then MsRs.

                         D) PRIORM OF SUPPORT: N/A

                         E) TOPOGRAPHIC SLJPPOIC: N/A

                         F) PROPOSM OPERATIONS: A new road status reporting system is
                being finalized. A qualitative MSR Report will be submitted daily to the
                ARcE"r Engineer via 416th Engineer Status Report (per SOP). A
                quantitative MM Report will be submitted weekly by separate
                correspondence.

                     C. ODRPS

                         l. VII CORPS/7TH ENGR BDE: Engineer Report #48 012400C MAR 91





                                                     G+5 PG 5

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 99 f:/Week-33/BX000525/COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL/operational summary 24 feb 91 g day:04189716374911
Control Fields 17
File Room = aug96_declassified
File Cabinet = Week-33
Box ID = BX000525
Unit = ARCENT
Parent Organization = CENTCOM
Folder Title = COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL
Folder Seq # = 9
Subject = OPERATIONAL SUMMARY 24 FEB 91 G DAY
Doc Seq # = 5
Doc Date =
Scan Date =
Queued for Declassification = 25-AUG-1996
SAGWI Request = 10-APR-1997
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 18-APR-1997