Subject = OPERATIONS DESERT SHIELD 82D ENGINEER BATTALION 28 AUG 91
Box ID = BX000301
Folder Title = 82D ENG BN AFTER ACTION REVIEW COMMENTS 5 APR 91
Unit = VII CORPS
Parent Org = ARCENT
9. PROJECT: Iraqi complex obstacle training area, 26 - 28 Dec 90.
DESCRIPTION: Constructed 200 meters of anti-tank ditch, 200
meters of berm, 200 meters of wire fence, 200 meters of minefield
and a platoon fighting position with communication trenches, to
replicate an Iraqi complex obstacle.
EQUIPMENT: Dozer - 10 hours
Bucket Loader - 15 hours
SEE - 72 hours
MAN HOURS: 75
UNIT: C Company, 82nd Engineer Battalion
10. PROJECT: 104th Finance Company survivability positions, 30
Dec 90.
DESCRIPTION: Constructed approximately 600 meters of
individual survivability trenches.
EQUIPMENT: SEE - 9 hours
MAN HOURS: 36
UNIT: C Company, 82nd Engineer Battalion
11. PROJECT: Perimeter berm and survivability positions for 75th
General Support Company, 31 Dec 90 - 2 Jan 91.
DESCRIPTION: Constructed approximately 3000 meters of berm,
and 500 meters of survivability trenches for the 75th General
Support Company.
EQUIPMENT: Dozer - 18 hours
SEE - 24 hours
MAN HOURS: 35
UNIT: D Company, 82nd Engineer Battalion
12. PROJECT: 16th Combat Support Group survivability positions, 2
Jan 91.
DESCRIPTION- Constructed approximately 500 meters of
individual survivability trenches.
EQUIPMENT: SEE - 2 hours
MAN HOURS: 6
UNIT: D Company, 82nd Engineer Battalion