Subject = OPERATIONS DESERT SHIELD    82D ENGINEER BATTALION  28 AUG 91   

Box ID = BX000301

Folder Title = 82D ENG BN AFTER ACTION REVIEW COMMENTS  5 APR 91                                               

Unit = VII CORPS   

Parent Org = ARCENT      






            13 - PROJECT:   Vehicle and individual survivability positions for
            210th Field Artillery Brigade, 3 - 8 Jan 91.

                DESCRIPTION: Constructed 2000 meters of berm, 48 Howitzer
            positions, 9 Fire Direction Center positions, Brigade Command and
            Control(C'-) positions, generator positions, shower points, and a
            100 meter X 100  meter trash pit.

                EQUIPMENT:   Dozer - 63 hours
                             Bucket loader - 47 hours
                             M916   250 miles
                             SEE   46 hours


                MAN HOURS:   82


                UNIT: 82nd   Engineer Battalion.

            14. PROJECT: Survivability positions for the VII Corps Tactical
            Area Command Post, 4 Jan 91.

                DESCRIPTION: Constructed approximately 200 meters of
            individual survivability trenches.

                EQUIPMENT: SEE - 8 hours

                MAN HOURS: 20


                UNIT: D Company, 82nd Engineer Battalion

            15. PROJECT: 87th Maintenance Battalion perimeter berm and
            survivability positions.

                DESCRIPTION: Constructed approximately 2000 meters of berm and
            300 meters of survivability trench.

                EQUIPMENT:   Dozer - 42 hours
                             M916 - 180 miles
                             Bucket Loader - 20 hours
                             SEE - 5 hours


                MAN HOURS: 67


                UNIT: D Company, 82nd Engineer Battalion

            16. PROJECT: 87th Chemical Company survivability positions, 10
            Jan 91.


                DESCRIPTION: Constructed 100 meters of survivability trench.

                EQUIPMENT: SEE - 8 hours

                UNIT: B Company, 82nd Engineer Battalion