Subject = OPERATIONS DESERT SHIELD 82D ENGINEER BATTALION 28 AUG 91
Box ID = BX000301
Folder Title = 82D ENG BN AFTER ACTION REVIEW COMMENTS 5 APR 91
Unit = VII CORPS
Parent Org = ARCENT
13 - PROJECT: Vehicle and individual survivability positions for
210th Field Artillery Brigade, 3 - 8 Jan 91.
DESCRIPTION: Constructed 2000 meters of berm, 48 Howitzer
positions, 9 Fire Direction Center positions, Brigade Command and
Control(C'-) positions, generator positions, shower points, and a
100 meter X 100 meter trash pit.
EQUIPMENT: Dozer - 63 hours
Bucket loader - 47 hours
M916 250 miles
SEE 46 hours
MAN HOURS: 82
UNIT: 82nd Engineer Battalion.
14. PROJECT: Survivability positions for the VII Corps Tactical
Area Command Post, 4 Jan 91.
DESCRIPTION: Constructed approximately 200 meters of
individual survivability trenches.
EQUIPMENT: SEE - 8 hours
MAN HOURS: 20
UNIT: D Company, 82nd Engineer Battalion
15. PROJECT: 87th Maintenance Battalion perimeter berm and
survivability positions.
DESCRIPTION: Constructed approximately 2000 meters of berm and
300 meters of survivability trench.
EQUIPMENT: Dozer - 42 hours
M916 - 180 miles
Bucket Loader - 20 hours
SEE - 5 hours
MAN HOURS: 67
UNIT: D Company, 82nd Engineer Battalion
16. PROJECT: 87th Chemical Company survivability positions, 10
Jan 91.
DESCRIPTION: Constructed 100 meters of survivability trench.
EQUIPMENT: SEE - 8 hours
UNIT: B Company, 82nd Engineer Battalion