Subject = OPERATIONAL SUMMARY 24 FEB 91 G DAY
Parent Organization = CENTCOM
Unit = ARCENT
Folder Title = COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL
Document Number = 5
Box ID = BX000525
A) itieater EPW Camps: Both BRONX and BROOKLYN are 98% complete
and can handle 48,000 EPWs eadi. BRONX has force main work remaining; EM
is 2 Mar. BROOKLYN has some collection, laundry, and shower, sump work
remaining and BM is 7 Mar. EPWs can use interim slit trenches if
necessary. Per G2 and DTA, present overall capacity is adequate.
B) Corps EPW Camps: Per Mff Sarigianis, XVIII ABN Corps has
all materials. VII Corps is apparently improvising for materials; MP
BDE constructing camp has not requested materials through ARCENT.
C) Pipeline:
1) Phase I: Flowing; has too much water. Filtering and
Fuel System Icing inhibitor will be used..
2) Phases II and III are complete.
3) Phase IV: no demand from LOM?ASES; will shut down to lay
15 miles of rigid pipe; ECD is 5 Mar.
3) Phase V is 193M4 to IOGBASE ALPHA. 145KK layed, 144KK
coupled, SSM aligned, tested and packed. Interim completion date is I
Mar. The ships Robert E. Lee, 961@M and President Polk have arrived; 85
miles of pipe awaitirg on dock for transportation. Pipeline unit does not
have haul capability at present. Will set up temporary fill station at
PS#7, 96]KM mark, while laying rigid pipe forward, then comeat to complete
193]KM nm to LOGBASE A. Final BM is 10 Mar.
D) Patriot Power: DHAHRAN battery is hooked up to commercial
power. U-MWM AB Battery Contractor left the Country. 535th EN DEr and
SUPCON engineer working; no ECD. Transfornex being installed at i(nA
site; BCD is 1 Mar. EM high voltage on or about 24 Feb at Riyadh AB, on
fourth site. Fixed generators. Contractors will deliver two
generator/trailers on 2 Mar; remainder on 5 Mar. All 12 mobile generators
and trailers are now in country.
E) ARCEU HQ Power: Transformer installed. 535th Ml DEr
preparing bill of materials for emergency power plan. SCECO began work at
School House on 18 Feb; EM is 28 Feb. SCECO began site work on 201st NI
Field Station on 18 Feb; EM is 28 Feb.
F) ESIW Army Airfield Power: The work request with guidance
has been forwarded to 2nd ASB,
G) 86th Signal BN Power: Plan for commercial power connection
has been forwarded to ARCERR G3.
H) CLass IV (Barrier):
1) Concertina: 13,500 rolls available at LOGBASE BRAVO;
2,200 rolls available at 321st MMC at DAMMAN.
2) Pickets: 129,000 each, various sizes, available at
IOGBASE BRAVO; 28,000 each, various sizes, are at 321st MMC.
3) Sandbags: 1,283,000(+) at 321st MMC and 3,900,000(+) at
LCG3ASE BRAVO.
4) Saudi-,controlled Class IV at IqM: BG Schardein to meet
with LTC Assaf.
G+3 PG 3
Document Page: First | Prev | Next | All | Image | This Release | Search
Document 99 f:/Week-33/BX000525/COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL/operational summary 24 feb 91 g day:04189716374911
Control Fields 17
File Room = aug96_declassified
File Cabinet = Week-33
Box ID = BX000525
Unit = ARCENT
Parent Organization = CENTCOM
Folder Title = COMMAND REPORT AFTER ACTION REPORT ENGINEER GE CELL
Folder Seq # = 9
Subject = OPERATIONAL SUMMARY 24 FEB 91 G DAY
Doc Seq # = 5
Doc Date =
Scan Date =
Queued for Declassification = 25-AUG-1996
SAGWI Request = 10-APR-1997
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 18-APR-1997